Bell Shoals Road Widening

Description

The project consists of widening the segment of Bell Shoals Road between Bloomingdale Avenue and Boyette Road from a two-lane, undivided rural road, to a four-lane, divided urban facility. The 3.1 mile corridor will have two vehicle lanes, a bike lane, and a sidewalk in both directions. A new traffic signal will be added at Starwood Avenue and the existing traffic signals at Glenhaven Drive, Rosemead Lane, and Bloomingdale Avenue will be upgraded. The project will also widen the existing bridge over the Alafia River, improve stormwater drainage, and enhance pedestrian safety features, including upgrades to comply with current ADA regulations.

The new design will increase the level of service along Bell Shoals Road, accommodating higher traffic volumes while maximizing safety along the corridor.

What to Expect

  • The work will involve heavy equipment and excavation, and will generate normal construction nise.
  • In some areas, traffic lane closures may be necessary. For the safety of the workers, pedestrians and other motorists, please observe all traffic control measures.
  • Construction will be in the right of way; however, at times it will be necessary to work on private property. All areas affected by the construction will be restored.
  • There will be extensive traffic control measures implemented during the construction. Please observe all traffic signs and be aware of potential shifts in traffic patterns.
  • Excavation work can sometimes cause an accidental water pipeline break or similar problem. As required by the Hillsborough County Health Department, instructions for a precautionary boil water notice will be issued for any water service interruption.

Cost & Funding

The $65 million construction project is being funded by Newland Communities and Hillsborough County.

All right of way acquisition is being processed and paid for by Hillsborough County. The bridge construction at the Alafia River and Bloomingdale Intersection improvements are also funded by Hillsborough County. All other design and construction costs related to the project will be funded by Newland Communities.

Timeline

Construction is expected to begin in fall 2018 and be finished in 2022.

Public Meetings

All past and upcoming public meetings for this project:

Contact

  • Project Manager - Thomas F. Rawls, P.E., Hillsborough County Public Works Department
  • For more information on this project, contact Public Works at (813) 635-5400 or through the At Your Service system

Additional Information